Meyer Contracting Inc. was contracted by the Metro Flood Diversion Authority for the General, Mechanical and Electrical Work for the construction of the OHB Ring Levee, Phases C and D, Package 43CD (WP-43CD) in Fargo, ND.
General Construction: Work includes general coordination of the 3 contractors, all civil site, process mechanical (including stormwater pumps and motors), structural, and architectural components.
Electrical Construction: Work includes electrical and instrumentation, sensors and controls (I&C) for four 80‐hp pumps, one variable frequency drive (VFD), switchgear, and motor control center, automatic transfer switch, panel, gas-detection system, 500 kW outdoor diesel generator, transformer, interior and exterior lighting, conduits, conductors, control wiring, communication components, connections and other associated electrical components.
Mechanical Construction: Work includes heating, ventilation, and air conditioning (HVAC)systems, electric unit heaters, HVAC piping, air handling, venting, ducting, motorized damper, louvres, and explosion-proof components.